Summary

The City of Concord is developing Substation N at 1050 Vinehaven Drive to add a 100 kV delivery point and 13 kV retail substation, increasing electric capacity and reliability for the growing Copperfield area.

Current stage: Under construction.

Current condition: Active.

Key Facts

Estimated Cost

No overall project cost is published.

Latest Progress

2025-11-13: Southeastern Consulting Engineers recommended Pike Electric's low responsive bid of $660,924.74 for Substation N subsurface construction; the bid review lists a 130-day delivery period.

Project Leaders

City of Concord
Project owner, Project sponsor

Project Funding

Funding type: Public · Status: Allocated

City of Concord: $660,925 (2025)

City of Concord: $184,644 (2025)

City of Concord: $4.33 million (2024)

City of Concord: $250,384 (2024)

Timeline

  1. Pike Electric recommended for subsurface construction

    Southeastern Consulting Engineers recommended Pike Electric's low responsive bid of $660,924.74 for Substation N subsurface construction; the bid review lists a 130-day delivery period.

    Stage after event: Under construction
  2. Sitework phase listed to begin

    An independent construction listing reports an April 17, 2025 start date for Substation N sitework and demolition. The date is retained as secondary reporting pending a City construction notice.

    Stage after event: Under construction
  3. Sitework and grading awarded

    Concord City Council recommended awarding Carolina Siteworks $184,644 for sitework and grading at 1050 Vinehaven Drive for Substation N.

    Stage after event: Under construction
  4. City authorizes circuit-switcher purchase

    The City authorized purchase of two 115 kV circuit switchers for Substation N through a Sourcewell cooperative contract at a quoted price of $250,384.28.

    Stage after event: Funded or programmed
  5. City awards major Substation N equipment packages

    Concord City Council awarded $4,334,604 in material bids for Substation N equipment including steel structure, transformers, circuit breakers, and metal-clad switchgear.

    Stage after event: Funded or programmed

Geography

Project site / location

  • Concord, NC
  • Cabarrus County, NC

Affected / impact geography

  • Concord, NC
  • Cabarrus County, NC

Map

ExactApproximate

Solid geometry is exact. Dotted geometry and dotted-outline markers are approximate. Multiple markers may show independently verified locations; they are not connected and do not establish a route or alignment.