Water and resilience
Yadkin Regional Water Supply Project
Location not confirmed
Verified Project Information
Summary
Union County and the Town of Norwood developed a regional drinking-water system that draws from Lake Tillery, treats water at a new Union County plant, and distributes treated water through the County's Yadkin River Basin service area.
Current stage: Completed or operational.
Key Facts
Estimated Cost
$300.00 million
as of 2023-09-22
Latest Progress
2024-02-13: Union County Water reported that water from the Yadkin River Water Treatment Plant first entered the customer distribution system on February 13, 2024, confirming operational use of the completed system.
Project Leaders
Town of Norwood
Project sponsor
Union County
Project owner, Project sponsor
Project Funding
Funding type: Public ยท Status: Allocated
Other funding contributors: Union County, Town of Norwood
Timeline
Yadkin water enters distribution system
Union County Water reported that water from the Yadkin River Water Treatment Plant first entered the customer distribution system on February 13, 2024, confirming operational use of the completed system.
Stage after event: Completed or operationalYadkin River Water Treatment Plant completed
Union County held the completion and ribbon-cutting event for the treatment plant, describing the broader Yadkin Regional Water Supply Project as complete after nearly two decades of planning, permitting, design, and construction.
Stage after event: Completed or operationalLake Tillery intake facility opens
Union County and Norwood celebrated the opening of the intake facility and pump station at Lake Tillery, a major raw-water component of the regional supply project.
Stage after event: Under constructionWater treatment plant construction begins
Union County announced the groundbreaking for the new Yadkin River Water Treatment Plant, part of the regional system being developed with Norwood. The plant was designed for an initial treatment capability of 12 million gallons per day.
Stage after event: Under constructionInterbasin transfer and project facilities documented
The State environmental record documents the proposed Lake Tillery intake and pump station, raw-water pipeline, Union County treatment plant, and finished-water delivery system, along with the project's interbasin-transfer framework.
Stage after event: Preliminary design or environmental reviewCounty and Norwood establish regional partnership
Union County and the Town of Norwood developed an interlocal intake and transmission partnership to secure a long-term Yadkin River Basin water supply for Union County's service area and Norwood.
Stage after event: Planning or feasibility
Geography
Project site / location
No site geography relationship is published.
Affected / impact geography
- Union County, NC
Map
No physical geometry is currently eligible for public mapping.
Visitor Feedback
60 visitor views
Keep this project current
Saw something different from the project information here?
Noticed new construction activity, changes, or information that differs from what we've reported? Share your observation to help us keep this project up to date.
Visitor Feedback
60 visitor views
Government Sources
- Supporting
- Supporting
- Primary
- Primary
- Primary
- Supporting
Media Coverage
No approved media coverage is currently published.