Poplar Tent Area Water Pump Station
Rock Hill Church tank site at 395 Stagecoach Road Northwest
Verified Project Information
Summary
Concord is constructing a 6-million-gallon-per-day drinking-water pump station at the Rock Hill Church water-tank site. The station will move finished water between service areas, improve supply redundancy, support growth, and replace the existing Rock Hill Church Road booster station. The $5.096 million construction contract is scheduled for final completion in May 2027.
Current stage: Under construction.
Current condition: Active.
Key Facts
Estimated Cost
No overall project cost is published.
Latest Progress
2025-11-15: The formal construction-services schedule set November 15, 2025 as the notice to proceed, with substantial completion scheduled for April 24, 2027 and final completion for May 24, 2027. Concord's current budget reporting confirms that construction began; no later official evidence of opening or completion was found in the bounded advancement scan.
Project Leaders
City of Concord
Project owner, Project planner, Project sponsor
Project Funding
Funding type: Public · Status: Allocated
City of Concord: $5.10 million (2025)
City of Concord: $612,450 (2025)
City of Concord: $477,000 (2024)
Timeline
Pump-station construction begins
The formal construction-services schedule set November 15, 2025 as the notice to proceed, with substantial completion scheduled for April 24, 2027 and final completion for May 24, 2027. Concord's current budget reporting confirms that construction began; no later official evidence of opening or completion was found in the bounded advancement scan.
Stage after event: Under constructionCouncil awards construction contract
After receiving four bids, City Council authorized a $5.096 million contract with low responsible bidder Harper General Contractors and a separate $612,450 construction-services amendment with Hazen and Sawyer. The construction bid exceeded an earlier estimate of about $3.5 million, primarily because of extensive site work on sloping terrain.
Stage after event: Contract awardedSix-mgd design issued for construction
Concord advertised Bid 2686 using issued-for-construction documents for a 6-mgd station, increasing the final design capacity from the earlier 5-mgd planning basis. The package included a pump building, generator, meter vault, access work, valve manholes, and about 1,250 feet of connecting pipe.
Stage after event: Final designHazen receives engineering contract
City Council selected Hazen and Sawyer from seven interested firms and authorized a $477,000 engineering and bid-phase services contract. The design basis initially called for 5 mgd at the Rock Hill Church tank property and identified projected demand from the Grounds at Concord as a primary driver.
Stage after event: Preliminary design or environmental reviewCity solicits pump-station design team
Concord issued RFQ 2600 for hydraulic analysis, site selection, preliminary and final civil, mechanical, and electrical design, bid documents, and an engineer's cost estimate. The Rock Hill water-tank property was identified as a preferred location.
Stage after event: Funded or programmedWater master plan recommends pump station
Concord's Water System Master Plan recommended a booster station identified as Rock Hill BPS. The project was subsequently included in the City's approved FY 2022-2026 capital improvement program.
Stage after event: Planning or feasibility
Geography
Project site / location
- Concord, NC
- Cabarrus County, NC
Affected / impact geography
- Concord, NC
- Cabarrus County, NC
Map
ExactApproximate
Solid geometry is exact. Dotted geometry and dotted-outline markers are approximate. Multiple markers may show independently verified locations; they are not connected and do not establish a route or alignment.
Visitor Feedback
85 visitor views
Keep this project current
Saw something different from the project information here?
Noticed new construction activity, changes, or information that differs from what we've reported? Share your observation to help us keep this project up to date.
Visitor Feedback
85 visitor views
Government Sources
- Primary
- Primary
- Primary
- Primary
- Primary
- Primary
- Primary
- Supporting
- Primary
- Primary
Media Coverage
ConstructConnect · 2025-10-30
Poplar Tent Area Water Pump Station - 5866299 (opens original source in a new tab)
ConstructConnect records the project at award stage with its contract value location scope and a reported November 2025 construction start.