Active transportation and recreation

Statesville Greenway Connector under U.S. 21

U.S. 21 greenway underpass


Final designDelayed

Verified Project Information

Summary

The City of Statesville plans a 0.5-mile grade-separated greenway connector beneath U.S. 21 in Statesville. The project would link the Gregory Creek and Fourth Creek greenway segments and close a gap in the local walking and bicycling network. Construction funding was later reduced and construction delayed.

Current stage: Final design.

Current condition: Delayed.

Key Facts

Estimated Cost

No overall project cost is published.

Latest Progress

2026-04-02: NCDOT's April 2026 project list states that $2,431,667 previously approved for construction was decreased and the project WBS closed because construction had been delayed. The action does not establish project cancellation.

Project Leaders

City of Statesville
Project owner, Project sponsor

North Carolina Department of Transportation
Project sponsor

Project Funding

Funding type: Public ยท Status: Changed

North Carolina Department of Transportation: $2.43 million (2026)

North Carolina Department of Transportation: $3.06 million (2025)

Other funding contributors: City of Statesville

Timeline

  1. NCDOT decreases approved construction funds

    NCDOT's April 2026 project list states that $2,431,667 previously approved for construction was decreased and the project WBS closed because construction had been delayed. The action does not establish project cancellation.

    Stage after event: Final design
  2. NCDOT delays construction to fiscal year 2026

    NCDOT's January 2026 Board action delayed construction from fiscal year 2025 to fiscal year 2026 to allow additional time for planning and design. The action listed $2.432 million in construction funding.

    Stage after event: Final design
  3. City advertises greenway connector bids

    The City of Statesville advertised EB-5818 for construction of a 0.5-mile hardscape pedestrian facility under U.S. 21 connecting approximately five miles of existing greenway. Bids were due December 18, 2025.

    Stage after event: Final design
  4. Earlier transportation funding record identifies connector

    NCDOT transportation-program records identify the Statesville Greenway connector under U.S. 21 as EB-5818 and describe the project as a bicycle and pedestrian connection between the Gregory Creek and Fourth Creek greenway segments.

    Stage after event: Funded or programmed
  5. Statesville addresses project funding shortfall

    A City of Statesville council record documents staff work to seek additional Surface Transportation Block Grant Direct Attributable funding for the greenway connector and identifies the City's local funding role.

    Stage after event: Funded or programmed

Geography

Project site / location

  • Statesville, NC
  • Iredell County, NC

Affected / impact geography

  • Statesville, NC
  • Iredell County, NC

Map

ExactApproximate

Solid geometry is exact. Dotted geometry and dotted-outline markers are approximate. Multiple markers may show independently verified locations; they are not connected and do not establish a route or alignment.