Active transportation and recreation
Avon Creek Greenway Extension
Avon Creek Greenway Extension trailhead at Second Avenue and South Belvedere Avenue
Verified Project Information
Summary
The Avon Creek Greenway Extension is a City of Gastonia project extending the existing Avon-Catawba Creeks Greenway in the Second Avenue and Belvedere Avenue area. It adds a multi-use path, sidewalks, curb and gutter, grading and related street improvements through the City's 2022 transportation bond program.
Current stage: Contract awarded.
Current condition: Active.
Key Facts
Estimated Cost
No overall project cost is published.
Latest Progress
2026-06-16: A June 2026 Gastonia council record and secondary meeting transcript report a $471,085.43 contract award to Quinn Sales, Inc. for the Avon Creek Greenway Extension. The reviewed evidence does not establish that physical construction had begun by the research date.
Project Leaders
City of Gastonia
Project owner, Project sponsor
Project Funding
Funding type: Public ยท Status: Allocated
Other funding contributors: City of Gastonia
Timeline
City awards greenway extension contract
A June 2026 Gastonia council record and secondary meeting transcript report a $471,085.43 contract award to Quinn Sales, Inc. for the Avon Creek Greenway Extension. The reviewed evidence does not establish that physical construction had begun by the research date.
Stage after event: Contract awardedCity advertises construction bid
The City invitation to bidders solicited construction proposals for the Avon Creek Greenway Extension from Second Avenue to Belvedere Avenue, with a public bid opening scheduled for January 29, 2026.
Stage after event: Funded or programmedCity reports bid advertisement and summer 2026 target
The City reported that the Avon Creek Greenway Extension was moving toward bid advertisement and expected completion by summer 2026. The later bid invitation and contract award supersede the earlier procurement expectation but do not establish construction start.
Stage after event: Funded or programmedExtension enters Gastonia transportation bond program
The City of Gastonia identified the Avon Creek Greenway Extension among projects supported by the voter-approved 2022 Transportation General Obligation Bond program.
Stage after event: Funded or programmed
Geography
Project site / location
- Gastonia, NC
- Gaston County, NC
Affected / impact geography
- Gastonia, NC
- Gaston County, NC
Map
ExactApproximate
Solid geometry is exact. Dotted geometry and dotted-outline markers are approximate. Multiple markers may show independently verified locations; they are not connected and do not establish a route or alignment.
Visitor Feedback
82 visitor views
Keep this project current
Saw something different from the project information here?
Noticed new construction activity, changes, or information that differs from what we've reported? Share your observation to help us keep this project up to date.
Visitor Feedback
82 visitor views
Government Sources
- Primary
- Primary
- Primary
- Primary
- Supporting
Media Coverage
MyTown ยท 2026-06-16
Gastonia council awards Avon Creek Greenway Extension contract (opens original source in a new tab)
MyTown's Gastonia council record reports a $471,085.43 contract award to Quinn Sales, Inc. for the Avon Creek Greenway Extension.