Silver Line Minimum Operable Segment – Airport to Coliseum/Ovens

Location not confirmed


Preliminary design or environmental reviewActive

Verified Project Information

Summary

The Charlotte Area Transit System's Silver Line Minimum Operable Segment is a planned light-rail project between Charlotte Douglas International Airport and the Coliseum/Ovens area. CATS describes the segment as approximately 10 miles with 16 stations. The FY 2027 adopted budget advances the Silver Line through 30% design and environmental review.

Current stage: Preliminary design or environmental review.

Current condition: Active.

Key Facts

Estimated Cost

$3.30 billion

as of 2024

Latest Progress

2026-06-11: The adopted FY 2027 budget identifies advancement of the Silver Line through 30% design and environmental review. CATS continues to list the Airport-to-Coliseum/Ovens MOS at 10 miles and 16 stations, with a $3.3 billion capital cost estimate in 2024 base-year dollars.

Project Leaders

City of Charlotte
Project owner, Project sponsor

Project Funding

Funding type: Public · Status: Allocated

No individual funding contributions are published.

Timeline

  1. FY 2027 budget advances design and review

    The adopted FY 2027 budget identifies advancement of the Silver Line through 30% design and environmental review. CATS continues to list the Airport-to-Coliseum/Ovens MOS at 10 miles and 16 stations, with a $3.3 billion capital cost estimate in 2024 base-year dollars.

    Stage after event: Preliminary design or environmental review
  2. Value-engineering options presented

    CATS presented potential Silver Line alignment, station, and design changes through its P.A.V.E. Act study. The presentation calls for further public and stakeholder input on options affecting project definition; it does not establish those options as adopted changes to the MOS.

  3. Adopted plan retains Airport-to-Coliseum MOS

    CATS's adopted 2055 Transit System Plan identifies the Silver Line MOS from Airport to Coliseum/Ovens and includes it in the fiscally constrained plan. The larger Belmont-to-Indian Trail LPA and future extensions are outside this project's scope.

  4. CATS begins 30% design development

    CATS reported that 30% design development began in July 2022 and that all four infrastructure design plan sets were received in 2024. Its March 2025 quarterly report said disposition of design comments remained underway; this does not establish completion of final design or environmental review.

    Stage after event: Preliminary design or environmental review
  5. Federal early scoping begins

    FTA and CATS issued an early-scoping notice to explore proposed light rail in Charlotte's West and Southeast corridors under the LYNX Silver Line name. This was early scoping, not a later formal environmental decision.

    Stage after event: Planning or feasibility

Geography

Project site / location

No site geography relationship is published.

Affected / impact geography

No separate impact geography is published.