Charlotte Gateway Station

Charlotte Gateway Station site at West Trade and Graham Streets


Preliminary design or environmental reviewDelayed

Verified Project Information

Summary

Charlotte Gateway Station is a planned multimodal passenger station and mobility hub at West Trade and Graham streets in Uptown Charlotte. Phase 1 rail infrastructure is complete, but the passenger station, bus facilities, and associated mixed-use development remain in design and delivery planning.

Current stage: Preliminary design or environmental review.

Current condition: Delayed.

Key Facts

Estimated Cost

No overall project cost is published.

Latest Progress

2026-02-04: Independent reporting in February 2026 found that the completed Phase 1 infrastructure still lacked a usable passenger entrance, waiting area and ticketing facility. Charlotte and the Metropolitan Public Transportation Authority were still determining how to move the station forward.

Project Leaders

Charlotte Area Transit System
Project planner, Project sponsor

City of Charlotte
Project owner, Project sponsor

North Carolina Department of Transportation
Project owner, Project sponsor

Project Funding

Funding type: Mixed public private · Status: Changed

Federal Railroad Administration: $30.00 million (2015)

Timeline

  1. Passenger station remains delayed and unopened

    Independent reporting in February 2026 found that the completed Phase 1 infrastructure still lacked a usable passenger entrance, waiting area and ticketing facility. Charlotte and the Metropolitan Public Transportation Authority were still determining how to move the station forward.

    Stage after event: Preliminary design or environmental review
  2. NCDOT considers an early temporary station

    NCDOT discussed a temporary or early station near the completed platform to begin passenger service before the permanent second phase. No final plan, cost or timeline was established in the reported records.

    Stage after event: Preliminary design or environmental review
  3. Phase 1 infrastructure is completed

    The first phase's track, structures and signal infrastructure was completed in October 2022. The rail infrastructure and platform were finished, but the passenger terminal, waiting area and ticketing functions remained for a later phase.

    Stage after event: Funded or programmed
  4. Phase 1 rail infrastructure construction begins

    Phase 1 construction began in summer 2018 and included new bridges, station tracks, signal infrastructure and an elevated high-level passenger platform.

    Stage after event: Under construction
  5. TIGER grant agreements authorize Phase 1 funding

    The City authorized grant and partner agreements for up to $30 million in federal TIGER discretionary funding for Phase 1a and 1b, with state and local funding supporting the phased project.

    Stage after event: Funded or programmed
  6. NCDOT receives Piedmont Improvement Program funding

    NCDOT reports that $52 million was awarded under the Piedmont Improvement Program for design, right of way and construction of Charlotte Gateway Station, which was included in the State Transportation Improvement Program.

    Stage after event: Funded or programmed
  7. Multimodal station feasibility study recommends Gateway site

    The Charlotte Multi-Modal Station and Area Track Improvements Feasibility Study recommended a new multimodal station near West Trade Street in Center City, now known as Charlotte Gateway Station.

    Stage after event: Planning or feasibility

Geography

Project site / location

  • Charlotte, NC
  • Mecklenburg County, NC

Affected / impact geography

  • Charlotte, NC
  • Mecklenburg County, NC