Transit
Red Line Commuter Rail – Charlotte Gateway Station to Mt. Mourne
Red Line corridor from Charlotte Gateway Station to Mt. Mourne
Verified Project Information
Summary
The Red Line is a proposed commuter-rail corridor from Charlotte Gateway Station through northern Mecklenburg County to Mt. Mourne in southern Iredell County. The project would use the existing Norfolk Southern O-Line, serve planned mobility hubs, and connect Uptown Charlotte with Huntersville, Cornelius, Davidson and the Lake Norman area.
Current stage: Preliminary design or environmental review.
Current condition: Active.
Key Facts
Estimated Cost
$1.40 billion
as of 2025
Latest Progress
2026-07: CATS identifies the next Red Line phase as a 30 percent design update with an approximate 18- to 24-month duration. The work includes finalizing station locations, selecting vehicle technology, completing NEPA documents and updating the cost estimate.
Project Leaders
Charlotte Area Transit System
Project planner, Project sponsor
City of Charlotte
Project owner, Project sponsor
Project Funding
Funding type: Public · Status: Allocated
City of Charlotte: $91.00 million (2024)
Timeline
30 percent design and NEPA phase begins
CATS identifies the next Red Line phase as a 30 percent design update with an approximate 18- to 24-month duration. The work includes finalizing station locations, selecting vehicle technology, completing NEPA documents and updating the cost estimate.
Stage after event: Preliminary design or environmental reviewMecklenburg voters approve transportation sales tax
Voters approved a one-cent Mecklenburg County sales tax projected to generate $19.4 billion over 30 years for transportation investments, including new rail lines. The tax became effective July 1, 2026, according to reported election information.
Stage after event: Funded or programmedRed Line design update reaches 15 percent
CATS reports that the Red Line Design Update concluded in October 2025 after updating the concept to a 15 percent design level, reassessing station locations and technologies, and producing an updated cost estimate.
Stage after event: Preliminary design or environmental reviewMTC adopts updated financially constrained transit plan
The updated Transit System Plan prioritized phased rapid-transit corridors, including the Red Line from Charlotte Gateway Station to Mt. Mourne.
Stage after event: Funded or programmedCity completes O-Line and Gateway property acquisition
Charlotte completed the purchase of approximately 22 miles of O-Line right-of-way and related rights for $74 million, plus approximately 1.6 acres near Charlotte Gateway Station for $17 million. The agreement preserved an option for a possible Iredell County extension.
Stage after event: Funded or programmedMTC adds Red Line advancement to the FY2023 CIP
The MTC amended the FY2023 Capital Investment Plan to include funding to advance the Red Line commuter-rail project.
Stage after event: Funded or programmedMTC adopts a North Corridor Locally Preferred Alternative
The MTC approved a new Locally Preferred Alternative for the North Corridor that retained a long-term Red Line vision while identifying near-term bus rapid transit on I-77.
Stage after event: Planning or feasibilityNorfolk Southern policy change stalls the project
Norfolk Southern changed its passenger-rail policy, and CATS reported that the Red Line was no longer feasible on the single-track O-Line under the new requirements.
Stage after event: Planning or feasibilityInitial Red Line design is completed
CATS reports that the initial Red Line design was completed in 2008 as part of the earlier North Corridor planning effort.
Stage after event: Preliminary design or environmental reviewMTC approves North Corridor commuter-rail study
The Metropolitan Transit Commission approved a major investment study for commuter rail along the I-77 North Corridor.
Stage after event: Planning or feasibilityNorth Corridor commuter rail is identified in transit planning
CATS traces the Red Line concept to the 2025 Transit and Land Use Plan, which identified a future commuter-rail connection in the North Corridor.
Stage after event: Planning or feasibility
Geography
Project site / location
- Charlotte, NC
- Davidson, NC
- Huntersville, NC
- Mooresville, NC
- Cabarrus County, NC
- Iredell County, NC
- Mecklenburg County, NC
Affected / impact geography
- Charlotte, NC
- Davidson, NC
- Huntersville, NC
- Mooresville, NC
- Cabarrus County, NC
- Iredell County, NC
- Mecklenburg County, NC
Map
ExactApproximate
Solid geometry is exact. Dotted geometry and dotted-outline markers are approximate. Multiple markers may show independently verified locations; they are not connected and do not establish a route or alignment.
Visitor Feedback
86 visitor views
Keep this project current
Saw something different from the project information here?
Noticed new construction activity, changes, or information that differs from what we've reported? Share your observation to help us keep this project up to date.
Visitor Feedback
86 visitor views
Government Sources
- Primary
- Primary
- Primary
- Supporting
- Primary
Media Coverage
Axios · 2025-11-04
Election results 2025: City council school board and transit tax increase (opens original source in a new tab)
Axios reports that Mecklenburg County voters approved a one-cent sales tax projected to support new rail lines, including the 25-mile Red Line commuter rail.
Axios · 2024-08-26
City has landmark deal to buy Red Line tracks land for $91M (opens original source in a new tab)
Axios reports on Charlotte's planned $91 million purchase of O-Line track and Gateway Station land and the remaining questions about the Red Line's cost and timeline.
Axios · 2024-04-17
Everything to know about the Red Line (opens original source in a new tab)
Axios describes the proposed Red Line, its planned stations, travel-time concept, renewed design work and the unresolved local funding question.