Summary
Charlotte Douglas International Airport's Terminal Lobby Expansion added 175,000 square feet, renovated 191,000 square feet, modernized passenger-processing areas, and improved terminal circulation and curbside access.
Current stage: Completed or operational.
Key Facts
Estimated Cost
$608.00 million
as of 2025-09-17
Latest Progress
2025-09-17: CLT celebrated completion of the Terminal Lobby Expansion after six phases of construction. The project added 175,000 square feet, renovated 191,000 square feet, and had a documented cost of $608 million.
Project Leaders
City of Charlotte
Project owner, Project sponsor
Project Funding
Funding type: Public · Status: Allocated
City of Charlotte: $608.00 million (2025)
Timeline
Terminal Lobby Expansion reaches completion
CLT celebrated completion of the Terminal Lobby Expansion after six phases of construction. The project added 175,000 square feet, renovated 191,000 square feet, and had a documented cost of $608 million.
Stage after event: Completed or operationalFinal checkpoint opens
The final checkpoint opened, completing the project's consolidation from five lettered checkpoints to three numbered checkpoints with 21 lanes.
Stage after event: Under constructionRoadway canopy completed
CLT completed the 146,000-square-foot roadway canopy that shelters passengers at the terminal curb front.
Stage after event: Under constructionTerminal skybridges open
Two pedestrian skybridges opened, connecting the terminal mezzanine with the Hourly Deck and improving protected circulation between parking and the terminal.
Stage after event: Under constructionQueen Charlotte statue unveiled
The restored Queen Charlotte statue was unveiled in the expanded lobby's Queens Court.
Stage after event: Under constructionWest ticket counters debut
West-side ticket counters opened as the Terminal Lobby Expansion progressed through its phased construction plan.
Stage after event: Under constructionFirst subterranean walkway opens
The first subterranean walkway and the west side of the expanded lobby opened as an early project phase.
Stage after event: Under constructionTerminal Lobby Expansion construction begins
CLT held the ceremonial groundbreaking on December 10, 2019, with construction beginning after the holiday season.
Stage after event: Under constructionCity Council approves construction contract
Charlotte City Council approved the Terminal Lobby Expansion construction contract. CLT later identified Holder-Edison Foard-Leeper Joint Venture as the contractor.
Stage after event: Contract awardedEarly Terminal Lobby Expansion planning begins
CLT reports that planning for the Terminal Lobby Expansion began in 2008 as part of the airport's long-term effort to modernize passenger facilities.
Stage after event: Planning or feasibility
Geography
Project site / location
- Charlotte, NC
- Mecklenburg County, NC
Affected / impact geography
- Charlotte, NC
- Mecklenburg County, NC
Map
ExactApproximate
Solid geometry is exact. Dotted geometry and dotted-outline markers are approximate. Multiple markers may show independently verified locations; they are not connected and do not establish a route or alignment.
Visitor Feedback
103 visitor views
Keep this project current
Saw something different from the project information here?
Noticed new construction activity, changes, or information that differs from what we've reported? Share your observation to help us keep this project up to date.
Visitor Feedback
103 visitor views
Government Sources
- Primary
- Primary
- Primary
- Supporting
- Supporting
Media Coverage
Construction Dive · 2025-10-06
Charlotte airport opens $608M terminal lobby expansion (opens original source in a new tab)
Construction Dive reports completion of CLT's $608 million terminal-lobby expansion, its added and renovated space, major features, and mixed airport-revenue funding.