Transportation

I-77 Express Lanes – North Corridor

I-77 from Brookshire Freeway/Exit 11 to N.C. 150/Exit 36


Completed or operational

Verified Project Information

Summary

A completed 26-mile managed-lane project on Interstate 77 from Brookshire Freeway in Charlotte to N.C. 150 near Mooresville. The $636 million project converted existing carpool lanes, added variably priced express lanes and direct connectors, and opened fully in November 2019. I-77 Mobility Partners operates and maintains the lanes under a 50-year public-private concession.

Current stage: Completed or operational.

Key Facts

Estimated Cost

$636.00 million

Latest Progress

2019-11-16: The remaining southern section opened 16 days after the contract deadline, making all 26 miles available to traffic. The completed project now operates with dynamic all-electronic tolling under the long-term concession.

Project Leaders

Federal Highway Administration
Project sponsor

I-77 Mobility Partners LLC
Project sponsor

North Carolina Department of Transportation
Project owner, Project planner, Project sponsor

Project Funding

Funding type: Mixed public private · Status: Allocated

North Carolina Department of Transportation: $94.70 million (2015)

Federal Highway Administration: $189.00 million (2015)

Timeline

  1. Full 26-mile corridor opens

    The remaining southern section opened 16 days after the contract deadline, making all 26 miles available to traffic. The completed project now operates with dynamic all-electronic tolling under the long-term concession.

    Stage after event: Completed or operational
  2. Full opening misses contract deadline

    NCDOT denied a completion extension, and liquidated damages began for three unfinished sections after the October 31 contractual deadline. The concessionaire attributed delays to added scope and other project conditions.

  3. Northern express-lane section opens

    The northern section from Hambright Road near I-485 to N.C. 150 opened to traffic while construction continued on the southern section toward uptown Charlotte.

  4. State audit finds no procurement impropriety

    A state audit reported no substantiated impropriety in the contract or award process. Independent reporting also recorded continuing criticism of the deal and concern about tolling and possible state liabilities.

  5. Independent contract review is completed

    NCDOT's independent consultant found no project risks or potential state liabilities that could not be managed with appropriate oversight, while also documenting public debate about tolling, alternatives, and the long-term concession.

  6. Corridor construction begins

    The project held its roadway groundbreaking and began construction. Sugar Creek Construction served as the lead contractor while design and right-of-way work continued under the integrated concession.

    Stage after event: Under construction
  7. Project reaches financial close

    The partners completed financing requirements after the $189 million TIFIA loan agreement and sale of $100 million in private activity bonds. Financial close allowed the project to proceed to construction.

  8. NCDOT signs 50-year concession agreement

    NCDOT and I-77 Mobility Partners signed the comprehensive design-build-finance- operate-maintain agreement. The selected proposal represented $647 million in total investment, including a rounded $95 million contribution from NCDOT and federal funds.

    Stage after event: Contract awarded
  9. Federal environmental review concludes

    FHWA and NCDOT completed the environmental review with a Finding of No Significant Impact for the I-77 high-occupancy/toll lane project between Exit 11 and Exit 36.

    Stage after event: Preliminary design or environmental review
  10. P3 developer procurement advances

    CRTPO incorporated express lanes from I-277 to N.C. 150 into its plans. NCDOT shortlisted four potential public-private developers and began detailed meetings that shaped the final procurement documents.

  11. Regional plan expands corridor scope

    CRTPO amended its long-range plan and transportation program to convert the existing HOV lanes, add a second express lane between I-85 and I-485, and build two express lanes between I-485 and Catawba Avenue.

  12. Regional board adopts express-lane strategy

    CRTPO adopted a resolution to develop express-lane projects on I-77, I-485, and U.S. 74 after a feasibility study examined converting and extending the existing I-77 carpool lanes.

  13. Regional study identifies I-77 North

    NCDOT and regional partners began the Fast Lanes Study. It identified the I-77 North corridor as a high priority for further express-lane planning.

    Stage after event: Planning or feasibility

Geography

Project site / location

  • Charlotte, NC
  • Cornelius, NC
  • Davidson, NC
  • Huntersville, NC
  • Mooresville, NC
  • Iredell County, NC
  • Mecklenburg County, NC

Affected / impact geography

  • Charlotte, NC
  • Cornelius, NC
  • Davidson, NC
  • Huntersville, NC
  • Mooresville, NC
  • Iredell County, NC
  • Mecklenburg County, NC