Transportation

I-85 Widening – Gaston County

Location not confirmed


Final designActive

Verified Project Information

Summary

The I-85 Widening – Gaston County program proposes widening approximately 10 miles of I-85 from six to eight lanes between U.S. 321 in Gastonia and N.C. 273 in Belmont, with interchange, roadway-bridge and railroad-bridge improvements.

Current stage: Final design.

Current condition: Active.

Key Facts

Estimated Cost

No overall project cost is published.

Latest Progress

2026-03-20: NCDOT's current project page lists phase-specific estimates of $587.705 million and $65.3 million for the Exit 17 section, $567.805 million and $41.9 million for the Exit 23–27 section, and $240 million for the bridge-replacement section. These estimates are retained separately rather than summed into an inferred program total.

Project Leaders

North Carolina Department of Transportation
Project owner, Project sponsor

Project Funding

Funding type: Public · Status: Allocated

U.S. Department of Transportation: $100.00 million (2022)

Other funding contributors: North Carolina Department of Transportation

Timeline

  1. NCDOT publishes current phase estimates

    NCDOT's current project page lists phase-specific estimates of $587.705 million and $65.3 million for the Exit 17 section, $567.805 million and $41.9 million for the Exit 23–27 section, and $240 million for the bridge-replacement section. These estimates are retained separately rather than summed into an inferred program total.

    Stage after event: Final design
  2. Geotechnical investigation begins ahead of widening

    NCDOT scheduled overnight lane closures to support geotechnical investigation for the future I-85 widening, including the South Fork Catawba River bridge and related structures in the Exit 23–27 segment.

    Stage after event: Final design
  3. NCDOT awards Exit 23–27 design-build contract

    NCDOT awarded Lane Construction a $337 million design-build contract for the four-mile segment between N.C. 7/Exit 23 and N.C. 273/Exit 27. Design work was underway and construction was expected to begin in summer 2026; this contract covers one section of the broader program.

    Stage after event: Final design
  4. I-85 Futures receives $100 million INFRA award

    The U.S. Department of Transportation awarded NCDOT a $100 million INFRA grant for the I-85 Futures scope, which includes widening, interchange and bridge improvements and multimodal and intelligent-transportation elements.

    Stage after event: Funded or programmed
  5. NCDOT holds public meetings on proposed widening

    NCDOT presented the proposed six-to-eight-lane widening, interchange improvements and bridge replacements for the Gaston County corridor during the project's public-meeting phase.

    Stage after event: Preliminary design or environmental review

Geography

Project site / location

No site geography relationship is published.

Affected / impact geography

No separate impact geography is published.

Map

No physical geometry is currently eligible for public mapping.